Another busy month sees not only a lot of work completed and ticked off the list, but many confirmed orders getting added at the other end, as well as several more enquiries about future works.
Work completed this month includes:-
Stan Peterson Close, Norwich – core cutting, vent pipe and vents for an air-con unit as well as replacement lead flashings, new gutters and downpipe.
Colindeep Lane, Sprowston – built-in double wardrobe with 4 doors.
Anne Close, Thorpe St Andrew – returned to replace existing ply staircase balustrading with open white square spindles.
Crow Road, North Walsham – a bedroom re-vamp including complete replastering, new door, skirtings, architrave and flooring.
Post Office Lane, Weston Longville – removing bathroom window and brick up ready for smaller replacement.
Meeting House Cottages, North Walsham – replace porch supports and wall plates.
Finally ended the month by stripping out an existing bathroom as a starter for next month’s main works at High Street, Mundesley.